Galway City Water Conservation Stage 3 Watermain Rehabilitation Works – Phase 1

On 19/05/2018, ShareRidge commenced work in Galway City on the Galway City Water Conservation Stage 3 Watermain Rehabilitation Project.

This Contract consists of the design, provision, construction, testing and commissioning of approximately 20km of PE100 and Ductile Iron watermain at various locations in Galway City and a small area of Galway County, including all valves, fittings, anchors blocks, connections, reinstatement and ancillary works.

The Contract includes the design, provision, installation and commissioning of new service pipes, boundary boxes. It also requires the decommissioning of replaced and otherwise redundant watermains and associated fittings, and the decommissioning of individual service pipes.